Re: [Planner] Flagging resource usage contention



Laurent Duperval wrote:
Hi,

I'm not sure how this is called, but is there a way to ask Planner to
show resources that are used more than they should? For example, if I
say that a user has to complete 4 2-day tasks in one week (5 days), it
should be flagged.

The resource usage view that was added in Planner 0.12 should be able to provide this kind of information.

Regards,
Richard

--