RE: 2.0.1 bug situation, esp. wrt ZVT



> 
> > 
> > We're already testing them, and have been for several weeks.
> > 
> > > Correct me if I'm wrong, but we are darn close to 2.0.2 already,
> > > aren't we?
> > 
> > We're still 4-5 weeks away.
> 
> hey 2.0.1 official release has still not happened  and then six more weeks 
before 2.0.2 right.
> 

Bharat,

Here's the schedule, don't believe it's changed. 2.0.1 was a 6 week 
schedule, but 2.0.2 is then a 4 week schedule. The 6 week schedule 
was to allow people to have a breather after 2.0

-Karl.

       July 2002
  Su Mo Tu We Th Fr Sa
      1  2  3 (4) 5  6  You Are Here :-)
   7  8  9 10 11 12 13
  14 15 16 17 18(19)20  FREEZE: Strings & User Interface for 2.0.1 & 2.0.2
  21 22 23 24 25(26)27  Weekly Snapshot
  28 29 30 31
  
      August 2002
  Su Mo Tu We Th Fr Sa
               1 (2) 3  Weekly Snapshot
   4  5  6  7  8 (9)10  RELEASE: G2D 2.0.1
  11 12 13 14 15 16 17
  18 19 20 21 22(23)24  Weekly Snapshot
  25 26 27 28 29(30)31  Weekly Snapshot
  
     September 2002
  Su Mo Tu We Th Fr Sa
   1  2  3  4  5 (6) 7  RELEASE: G2D 2.0.2
   8  9 10 11 12 13 14
  15 16 17 18 19 20 21
  22 23 24 25 26 27 28
  29 30