Re: [Planner Dev] bug report (and link on contact page is broken)



On ons, 2004-03-24 at 10:34 -0500, Isaac Jones wrote:

Hi,

> I'm sorry if this is a known bug.  The gnome bug tracking link from your
> contact page is broken.

Which page are you looking at? 

The bugzilla link at:
http://planner.imendio.org/contact/

should work.

> Perhaps this is not a bug, but this behavior has been driving me a
> little nuts in the 0.11 release, and I just grabbed the CVS release and
> it's there too.
> 
> If I assign a total amount of resources to a task that is not equal to
> 100%, then dragging the right end of a task in the gantt chart (to
> resize it) it jumps either higher or lower, I assume, depending on the
> amount of work.
> 
> So I assume what's happening is a confusion between the total work time
> verses the calendar time.  To reproduce:
> 
> - Create a new project
> - create a new resource
> - create a new task
> - set the task to take 2 weeks
> - assign your resource, at 50%, to the task. it should jump to 4 weeks
> - try to shrink the task to 1 week (note that it jumps to 2 weeks)
> 
> So this kinda makes sense, if I were ever dragging the Ghantt chart bar
> to indicate how many man-hours something is going to take, but that's
> not usually what I want to do. I drag the bar to the position I want it
> to be in (in wall-clock time, since that's what the ghantt chart is
> showing me), and planner should compute how many man-hours it now
> becomes.

Have these issues been added to bugzilla already? Just wanted to make sure 
that they where not lost in the archives.

Regards,
  Mikael Hallendal
-- 
Imendio HB, http://www.imendio.com/