[Planner Dev] Suggestion for project tracking planned v. actuals using Phase as a commit/restore tag.
- From: "lincoln phipps openmutual net" <lincoln phipps openmutual net>
- To: Planner Project Manager - Development List <planner-dev lists imendio com>
- Subject: [Planner Dev] Suggestion for project tracking planned v. actuals using Phase as a commit/restore tag.
- Date: Tue, 20 Apr 2004 21:14:30 +0100
Been bugging me to discuss this - Baselines (as MS Project
Refers to them) and how do we implement the same in Planner ?.
My thoughts today as I was dumping garden rubbish at
the local refuse tip, was this......
My idea is: We have a Project Phase so we should be able
to "commit" a phase and have the current tasks, work, duration,
completion and resource assignments (including costs)
remembered/tagged with that Phase.
Thus we're not constrained to just 1 "Baseline" but many.
If someone wants to call a Phase "Baseline" so be it.
So I envisage a button of "Commit Phase". Which snapshots
the above stuff for this into the XML datafile/database.
You should thus be able to "Rollback" to a particular
Phase or also report of differences (in later versions
of Planner :) ).
Thoughts ?.
rgds,
Lincoln.
[