Re: [Planner Dev] Planner - Suggestion for Deliverable or Objective view.



On fre, 2004-07-09 at 13:31 -0400, Kurt Maute wrote:

> Finally, I've always struggled with a good way to get MSP to show me a
> concise view of what tasks should be active in the current and next week
> or so.  In other words, I've got to manually scan down my plan for tasks
> that should have started already or are about to start, and tasks that
> should have finished already or should be finished soon.  This is a
> special pain with larger plans.  I'm not sure if this would need to be a
> separate view, or a variation of the view you're proposing.

It could be useful with a separate view/report that shows the current
situation in some way. Somewhat like the old summary view in Evolution.

/Richard

-- 