[Planner Dev] Incorrect Start Dates in Tasks View
- From: John_Minkle huntalternatives org
- To: Planner Project Manager - Development List <planner-dev lists imendio com>
- Subject: [Planner Dev] Incorrect Start Dates in Tasks View
- Date: Mon, 7 Jun 2004 17:58:06 -0400
An example: Task A is a one Day Task
that takes place Friday and it is linked to Task B. Task B shows
that it starts on Friday in the Tasks View. But in the Gantt View it is
clear that the task does not start until Monday.
I am writing the list because I hope
I can get this fixed. I am trying to get a small group of people to use
Planner at our org. To make a long story short, I would be
really nice if this could be fixed.
I have compiled the source from CVS
on a Mandrake 10.0 system here. I am planning to have them use the compiled
binary. I tried to find the code for the Start column myself but
I am running out of time.
-john
[