[Planner Dev] bug report (and link on contact page is broken)



I'm sorry if this is a known bug.  The gnome bug tracking link from your
contact page is broken.

Perhaps this is not a bug, but this behavior has been driving me a
little nuts in the 0.11 release, and I just grabbed the CVS release and
it's there too.

If I assign a total amount of resources to a task that is not equal to
100%, then dragging the right end of a task in the gantt chart (to
resize it) it jumps either higher or lower, I assume, depending on the
amount of work.

So I assume what's happening is a confusion between the total work time
verses the calendar time.  To reproduce:

- Create a new project
- create a new resource
- create a new task
- set the task to take 2 weeks
- assign your resource, at 50%, to the task. it should jump to 4 weeks
- try to shrink the task to 1 week (note that it jumps to 2 weeks)

So this kinda makes sense, if I were ever dragging the Ghantt chart bar
to indicate how many man-hours something is going to take, but that's
not usually what I want to do. I drag the bar to the position I want it
to be in (in wall-clock time, since that's what the ghantt chart is
showing me), and planner should compute how many man-hours it now
becomes.

peace,

isaac

-- 
Isaac Jones <isaac jones aetion com>
Aetion




[Date Prev][Date Next]   [Thread Prev][Thread Next]   [Thread Index] [Date Index] [Author Index]