Richard Hult wrote:
On lör, 2004-05-01 at 07:53 +0100, lincoln phipps openmutual net wrote:

Been thinking about how the current scheme in Planner
has a number of places that have humans created with their
attributes (email, phone etc) as manager roles and which
I feel should be brought into their own class.


We definitely need to work on the resource handling in Planner, but any
larger changes will be post-1.0.

OK - probably right for post 1.0 as its a sizable change.

For now, I'd like to focus on the low hanging fruit that we can fix for
1.0, perhaps like having fixed cost and things like that for resources.
Any ideas in that area?

My current bugzillas on resources and costs are,

Add multi-currency support for resource costs....
http://bugzilla.gnome.org/show_bug.cgi?id=138935

Resource costs should have a per-use cost value....
http://bugzilla.gnome.org/show_bug.cgi?id=138936

Resource costs should be more flexible on time period...
http://bugzilla.gnome.org/show_bug.cgi?id=140252

and can't actually think of anything else to do on that
other than we should look at implementing the standard (as
it is now) and overtime rates (this isn't bugzilla'd) .
We'll never get a perfect implementation of the wide variety
of how much people cost (i.e. weekend v. holiday v. special
holidays v. T+1/2 or double time or shift allowances ....)
so the two rates + fixed rate will suffice.

Lincoln.


/Richard


_______________________________________________
Planner-dev mailing list
Planner-dev lists imendio com
http://lists.imendio.com/mailman/listinfo/planner-dev




[Date Prev][Date Next]   [Thread Prev][Thread Next]   [Thread Index] [Date Index] [Author Index]