Re: [Planner Dev] Fixed dates on tasks?



On ons, 2004-05-19 at 17:28 -0400, Charles Tryon wrote:
>   I've seen the dialog box, but I still didn't find any place to assign
> either a start or finish date.

You need to select the Task view and click the start date cell and
select a "Must start on" constraint (or "Start no earlier than").

/Richard

-- 
Imendio HB, http://www.imendio.com/