Re: [Planner Dev] Fixed dates on tasks?
- From: Richard Hult <richard imendio com>
- To: Planner Project Manager - Development List <planner-dev lists imendio com>
- Subject: Re: [Planner Dev] Fixed dates on tasks?
- Date: Thu, 20 May 2004 00:51:05 +0200
On ons, 2004-05-19 at 17:28 -0400, Charles Tryon wrote:
> I've seen the dialog box, but I still didn't find any place to assign
> either a start or finish date.
You need to select the Task view and click the start date cell and
select a "Must start on" constraint (or "Start no earlier than").
/Richard
--