Re: [Planner Dev] Some bugs/RFE



Santiago Erquicia wrote:
Hi,

Hi,

1- In the Gantt Chart I cannot specify durations in months, only days.

You can use a few units by using a suffix, d, w, h works. We have been talking on and off about how to solve this nicely. I don't think we have a bug report in bugzilla though.

2- If I choose that a task has a fixed duration, I cannot specify the
finish date in the Task View.  I just can specify the work.  Shouldn't
we have a Duration column in this view and allow to change it's value if
the task has a fixed duration and don't allow to change the work?

Yes, I think having a duration column there would be a good idea.

3- There isn't any way, at least that I could find, to specify in the
project or Planner itself if tasks are going to be work or duration
driven.  If there were, what would be better in the Gantt Chart, show
the work or duration column?

I'm not sure. If we had more space, we could show both and have to correct one be editable...

4. While I'm changing the finish date of a task in the Gantt Chart, it
would be good if when I reach the right limit of the screen that it
scroll automatically.  Now I need to unclick it, scroll a little, move
the final date again.  This is specially a problem when you cannot
insert anything different than dates.

Yes, agreed.

5. The new project starts at the current day by default.  When I change
the project starting date to a future date and click in some other place
I can see how the Task View is updated.  As soon as I click the close
button, it goes back to the previous date of the one that I selected.

I can't reproduce this in HEAD.

6. If I set a task as fixed duration, shouldn't it gray out the box of
the necessary work to accomplish it?  I mean, shouldn't it happen the
opposite as what happens when it is work driven?

Well, the way we handle fixed duration is by changing the assignments. That is, if a task has fixed duration and you change the work or duration, the resource assignment is tweaked to adjust to the new workload/duration.

7. There should be a task edit button or resource button on the toolbar,
depending the view.  This is the most common action to perform in those
views.

Hm, would probably be a good idea.

8. When editing the relationships between tasks there is no clear
indication of the unit of time used for lag.

We have a bug report for this:

http://bugzilla.gnome.org/show_bug.cgi?id=132357

9. If you enter a task in the Gantt Chart where its name is longer than
the current Name column, it automatically resizes it.  Shouldn't it be
the opposite?  I don't want to be changing every time I add a new task
the separator between the table and the graph to see the Work column.

I'm pretty much waiting for GTK+ 2.6 since it's trivial to fix with that version. We could add some kind of workaround for now though, that ellipsizes the text if it's too wide. It's probably a good idea.

This is what I have founded until now.  If you think this is worth to
put into bugzilla, please let me know which ones.

Thanks, lots of good feedback. Feel free to add them to bugzilla :)

/Richard

--