Re: [Planner Dev] Cost Calculation Fix



On Tue, 2005-11-29 at 22:23 -0600, ZAXIOM Solutions LLC wrote:
> Dev Team:
> 
> We have developed a fix for an issue with version 0.13 we discovered.
> The task cost calculation is incorrect. The error of the cost is
> introduced by the integer representation of the units. For example, a
> fixed duration task with 1 day of work and 8 days duration assigned to
> a single resource results in a unit percentage of 13 instead of 12.5.
> Therefore, the resulting cost of the task is 416 instead of 400 when
> using a resource cost of 50; this reflects the difference between
> 12.5% * 8 days * 8 hours * $50 and 13% * 8 days * 8 hours *$50.
> 
> To fix this, we converted units to a gfloat instead of a gint. We have
> tested our solution, and all seems to be well. We would like to
> contribute our changes to the project. Who do we need to get the
> updated files to? 

Sounds great!  Send a patch file to this list and I'll have a look.

tnx!


-- 
Kurt Maute <kurt maute us>




[Date Prev][Date Next]   [Thread Prev][Thread Next]   [Thread Index] [Date Index] [Author Index]