Alexandre Poltorak wrote:
Hello all!
Hi,
pls, why if i assign a task to more one resource i need 120% to have the
same time in "Work" & "Duration"?
I'm not sure I understand what you mean, could you elaborate? Have y you
tried to latest version (0.13)?
Also what is Slack?
It's described in the user guide. It's the amount of time a task can be
delayed without delaying the whole project.
As suggestion: I'll find really useful to have Polto [30%] also in the
Task view. as on the Gant view.
Good idea, we could add the percantag in the task view to the "assigned
to" column. Feel free to file a bug report on this.
/Richard
--