Re: [Planner Dev] Resource feedback



-----BEGIN PGP SIGNED MESSAGE-----
Hash: SHA1

Hi,

first of all excuse me for my poor english! :-)

Before expose my needs I want to thank you for your very good work on
planner. I'm using it at work for several weeks instead of PMW.

The "missing feature" is, for me, the ability to set "variable" the unit
in the association task-ressource. Actually, it could be great if
planner could do:


Task 1: personn A: **********+++++*****
Task 2: personn A:           +++++

100%: ****
50%:  ++++

Task 1 duration should be recomputed instead of setting person A
"over-loaded"...

I know these kind of features need to be more described. But here's only
my need.

Regards!

Alvaro del Castillo wrote:
> Hi!
> 
> First of all, the target of this email is to share some needed features
> and ideas to implement them. I plan to find time to work on it.
> 
> I know we have had long discussions in the past about how the resources
> of a project should feedback the project manager in order the schedule
> for the project could be updated. 
> 
> I have been talking with a mate in the work that is working scheduling
> projects (with MS Project for now) as me and we have started to have a
> clear vision of a minimal implementation that we need.
> 
> 
> 				     >	Resource 1
> 
> 
> 				     >	Resource 2
> 
> 	Project Manager --> Planner
> 				     >	Resource 3
> 
> 					..........
> 					
> 				     >	Resource n
> 
> 
> The project manager once the schedule is completed wants to communicate
> it to the resources. Currently we have the export as HTML report and it
> is a nice way to do it, but what we really need is a individual report
> per resource in order each resource doesn't get confused with the
> complete and normally complex schedule of the project.
> 
> So the first thing we need is to improve a bit how to communicate the
> individual schedule to the resources, maybe with a new style sheet that
> creates a individual page per resource.
> 
> Once a resources has its own view of the schedule she can easily report
> feedback about the progress on her tasks using this view. It could be
> ideal that the per resource report include a little GUI in order the
> resource can feedback about the completion status of the work.
> 
> A quick idea could be to offer the report as a HTML page, like the
> actual HTML complete schedule report, with a button to indicate the
> completion of a task.
> 
> Once a user hits the button a CGI (I think we have had a CGI in the past
> in MrProject) could be invoked that updates the schedule in Planner
> obtaining a lock against the planner file before modifying it.
> 
> Currently planner is designed as a single user application but with a
> very basic blocking system using lock files, we can have a good
> concurrent control system.
> 
> With this simple schema we start to give Planner feedback about
> execution and I feel it will be a more useful tool for managing the
> execution of projects.
> 
> Any ideas or comments will be very welcomed. I will rethink a bit all
> the design before starting to code anything.
> 
> Cheers
> 
> 
> ------------------------------------------------------------------------
> 
> _______________________________________________
> Planner-dev mailing list
> Planner-dev lists imendio com
> http://lists.imendio.com/mailman/listinfo/planner-dev

-----BEGIN PGP SIGNATURE-----
Version: GnuPG v1.4.3 (GNU/Linux)
Comment: Using GnuPG with Mozilla - http://enigmail.mozdev.org

iD8DBQFEQ8o9v2w7Uh8v4hcRAtlBAJ0Y1TseuX1KDfGSWFvMjgrJzvyMjgCfZUGJ
qtBUdXK1F5yf8rnfkQWUlWg=
=+uJh
-----END PGP SIGNATURE-----



[Date Prev][Date Next]   [Thread Prev][Thread Next]   [Thread Index] [Date Index] [Author Index]