Hi guys, If a task uses all working time of a day and the gantt is zoomed out to the point where the non-working time of a day is not grey anymore, the task should cover the entire day, even if it's the first or last day of the task. Reasoning here is: if an interval in the gantt chart cannot be recognised as non-working when looking at the chart because it has a white background, then not extending the task to include this interval looks like the task does not cover the entire day. Do you agree that this is how it should work? Maurice. -- Maurice van der Pot Gentoo Linux Developer griffon26 gentoo org http://www.gentoo.org Creator of BiteMe! griffon26 kfk4ever com http://www.kfk4ever.com
Attachment:
pgpqCA3tpbG1C.pgp
Description: PGP signature