Task bars should be extended to include any non-working time that is not shown as such



Hi guys,

If a task uses all working time of a day and the gantt is zoomed out to
the point where the non-working time of a day is not grey anymore, the
task should cover the entire day, even if it's the first or last day of
the task.

Reasoning here is: if an interval in the gantt chart cannot be
recognised as non-working when looking at the chart because it has a 
white background, then not extending the task to include this interval
looks like the task does not cover the entire day.

Do you agree that this is how it should work?

Maurice.

-- 