Moving tasks to be done to after today



What if planner would always put completed (parts of) tasks left of
today and uncompleted (parts of) tasks right of today?

Imo this would have the advantage that it is more clear when you are
behind or ahead of schedule.

The way I envision it, it would:
- split tasks that have been partly completed

  (upper case is completed, lower case is the part still to be done)

        today
          |
  AAA     aaaa
     BBBBB    bbbb

- join multiple small completed parts of a task into 1, so suppose you
  work on task 'a' for 2 days. Afterwards it would be:

          today
            |
  AAAAA     aa
       BBBBB  bbbb

  instead of:

          today
            |
  AAA     AAaa
     BBBBB    bbbb

  This is just to prevent cluttering the plan when you work on multiple
  tasks in parallel.

Thoughts?

Regards,
Maurice.

-- 
Maurice van der Pot

Gentoo Linux Developer   griffon26 gentoo org     http://www.gentoo.org
Creator of BiteMe!       griffon26 kfk4ever com   http://www.kfk4ever.com