Managing the triple constraints appropriately
- From: "Anmar Oueja" <anmar canada com>
- To: planner-dev-list gnome org
- Subject: Managing the triple constraints appropriately
- Date: Thu, 3 Apr 2008 22:15:43 -0700
Hello Guys:
I have been playing with planner 0.14 and I noticed that we don't include the efficiency/availability/utilization in our work and duration calculations. In other words, if I enter work to be 3 days, duration is automatically 3 days. This is correct if the utilization is 100% but that is not always. Many times people are working on two activities at once with 50% utilization for each.
Work
Duration = -------------------
Utilization
p.s. I am using Utilization but we can name is efficiency or availability.
I think this is a very fundamental for any PM tool that is planning on going places. Do you know if our engine handles such an issue.
Your thoughts pleas?