On Tue, Apr 29, 2008 at 08:03:57AM -0400, Mario Rincón wrote: > Hi!. I have a question about Planner database schema (version 0.13). The > thing is that I have been studying it, in order to integrate it with > functionality existent in another tool, and I cannot figure out what is the > function of the std_rate and ovc_rate fields in the resource table. So, what > is their function?. std_rate is the cost of a resource per hour. If a resource has a cost of 250 and he works on a task at 100% for 1 day, it'll cost 2000. This total for the task is also visible in cost column of the task list. ovt_rate (not ovc_rate) is currently not used in the source code, but was meant for overtime cost of a resource. Hope this helps. Regards, Maurice. -- Maurice van der Pot Gentoo Linux Developer griffon26 gentoo org http://www.gentoo.org Gnome Planner Developer griffon26 kfk4ever com http://live.gnome.org/Planner