Re: missing calculation work day for html



On Sat, Oct 25, 2008 at 11:58:58PM +0900, dev xmesoft com wrote:
> I found problem in html output.
> i.e.
> Set to start time 10:00 to 13:00 and 14:00 to 17:00 (6 hour of day)
> Insert a task need in gantt WBS and set to 4 days work.
> After that extend output with html
> check work day is 3 days  instead of 4 days.

I thought there was a report for this in bugzilla, but I am unable to
find it. Could you file a new report for this?

The problem is with the assumption in planner2html.xsl that a day is
28800 seconds. I think it should use the definition of the "Working"
day, but I'll have to check the planner source to see what it normally
does.

Maurice.

-- 
Maurice van der Pot

Gentoo Linux Developer   griffon26 gentoo org    http://www.gentoo.org
Gnome Planner Developer  griffon26 kfk4ever com  http://live.gnome.org/Planner