Re: Overtime with planner



Hi Phù,

You could somehow do this by creating a another calendar permitting this
exta hours and create a second resource with another cost. Per example:

John Smith: 150$/h
John Smith(EH): 290$/h

The second JS(EH) would be assigned to the same task but his particular
calendar would only contain hours from 18pm to 21pm.

This is a workaround, of course.

Any got better idea ?

Max


Le lundi 16 février 2009 à 19:34 +0700, Do Minh Phu a écrit :
> Dear Planer Developers
> I'm a Vietnamese, I use Planner for my project. But there is no function 
> about overtime in Planner
> Example, Every day, every one work from 8am to 17pm.
> I try to assign someone work from 18pm to 21pm with cost is double.
> 
> Hope developers will develop function about overtime for Planner.
> Thanks
> Best regard,
> 
> Phú
> 
> _______________________________________________
> Planner-dev-list mailing list
> Planner-dev-list gnome org
> http://mail.gnome.org/mailman/listinfo/planner-dev-list