Hi Phù,
You could somehow do this by creating a another calendar permitting this
exta hours and create a second resource with another cost. Per example:
John Smith: 150$/h
John Smith(EH): 290$/h
The second JS(EH) would be assigned to the same task but his particular
calendar would only contain hours from 18pm to 21pm.
This is a workaround, of course.
Any got better idea ?
Max
Le lundi 16 février 2009 à 19:34 +0700, Do Minh Phu a écrit :
> Dear Planer Developers
> I'm a Vietnamese, I use Planner for my project. But there is no function
> about overtime in Planner
> Example, Every day, every one work from 8am to 17pm.
> I try to assign someone work from 18pm to 21pm with cost is double.
>
> Hope developers will develop function about overtime for Planner.
> Thanks
> Best regard,
>
> Phú
>
> _______________________________________________
> Planner-dev-list mailing list
> Planner-dev-list gnome org
> http://mail.gnome.org/mailman/listinfo/planner-dev-list
[
Date Prev][Date Next] [
Thread Prev][Thread Next]
[
Thread Index]
[
Date Index]
[
Author Index]