Re: about the Planner PERT changes review from Maurice Van Der Pot



3) The PERT functionality does not seem to work with summary tasks.
Suppose A is a summary task, B its subtask and task A can't start
until C has been finished. Then in the PERT chart I can see A after
C, but B is parallel to C.
Yup, I forgot to mention it. The diagram works up to the first level of the task tree. My project drained all the time I had, so I didn't implement the summary tasks.

4) There doesn't seem to be enough room for durations in the PERT chart.
I think it happens when a task duration is "7d 4h" or "138d".
Do you have some ideas to do it properly? The size of the nodes is fixed, so I didn't see any solution except cropping.

5) Task names seem to be modified if they are too long to fit in the
PERT chart. This modification then also shows up in the task list and in
the Gantt chart. I think pango can render text within a limited space
and render ellipsis when necessary, so you won't have to change the text
itself. In fact I think that's already being done for durations like
"7d 4h".
Oh, I wasn't aware of that. Sorry. I'm going to fix it when I have the time (past exams and such...).
 
6) At one point I had a missing box in the PERT chart. Not sure what it
was, but if I see it again I'll let you know.
Thanks.

7) Because the PERT chart has no easy correspondence between the boxes
and the tasks in the list on the left, I think it would be nice to have
some indicator for when a task is selected (different color, fat border,
...)
I got the idea but I somehow dropped it on the way. I'll add it too.

2009/6/17 <planner-dev-list-request gnome org>
Send Planner-dev-list mailing list submissions to
       planner-dev-list gnome org

To subscribe or unsubscribe via the World Wide Web, visit
       http://mail.gnome.org/mailman/listinfo/planner-dev-list
or, via email, send a message with subject or body 'help' to
       planner-dev-list-request gnome org

You can reach the person managing the list at
       planner-dev-list-owner gnome org

When replying, please edit your Subject line so it is more specific
than "Re: Contents of Planner-dev-list digest..."

Today's Topics:

  1. Re: Addition of PERT functionalities to Planner + slip line.
     (Maurice van der Pot)


---------- Message transféré ----------
From: Maurice van der Pot <griffon26 kfk4ever com>
To: planner-dev-list gnome org
Date: Tue, 16 Jun 2009 22:33:31 +0200
Subject: Re: Addition of PERT functionalities to Planner + slip line.
On Sun, Jun 14, 2009 at 04:56:56PM +0200, Gabriel Camby wrote:
> I'll be glad if you tell me what you think of it.

First of all, nice work! I'm sure this functionality will be useful for
a lot of our users.

Here's a couple of things I noticed during my initial review:
1) The patch is not well formed. It has white space issues (git apply
complains) and has Windows line endings in it.

2) Let's call the center of the edge between the completed part of a
task and the part that still needs to be done the "progress point".
The slipline is a vertical line at a selected date that goes from
selected date above the task bar to the progress point and then back to
the selected date below the task bar.

Because the slip line crosses the edges of the task bar about half-way
between the progress point and the selected date, it looks to me like
things are not as far behind or ahead of planning as they really are.

I think that if the slipline would connect to task bar edges above and
below the progress point, it would be clearer.

Then again, maybe I'm completely wrong here and everybody is used
to have sliplines like they are now. I'm not a project manager.
Anyone with project management experience, please chip in =)

3) The PERT functionality does not seem to work with summary tasks.
Suppose A is a summary task, B its subtask and task A can't start
until C has been finished. Then in the PERT chart I can see A after
C, but B is parallel to C.

4) There doesn't seem to be enough room for durations in the PERT chart.
I think it happens when a task duration is "7d 4h" or "138d".

5) Task names seem to be modified if they are too long to fit in the
PERT chart. This modification then also shows up in the task list and in
the Gantt chart. I think pango can render text within a limited space
and render ellipsis when necessary, so you won't have to change the text
itself. In fact I think that's already being done for durations like
"7d 4h".

6) At one point I had a missing box in the PERT chart. Not sure what it
was, but if I see it again I'll let you know.

7) Because the PERT chart has no easy correspondence between the boxes
and the tasks in the list on the left, I think it would be nice to have
some indicator for when a task is selected (different color, fat border,
...)


That's it for today.


Thanks,
Maurice.

--
Maurice van der Pot

Gentoo Linux Developer   griffon26 gentoo org    http://www.gentoo.org
Gnome Planner Developer  griffon26 kfk4ever com  http://live.gnome.org/Planner


_______________________________________________
Planner-dev-list mailing list
Planner-dev-list gnome org
http://mail.gnome.org/mailman/listinfo/planner-dev-list




[Date Prev][Date Next]   [Thread Prev][Thread Next]   [Thread Index] [Date Index] [Author Index]