Re: [Planner] Anyway to start an independent task at an arbitrary date other than project start date?



Gary Carter wrote:

Hi,

1) Is there anyway to start an independent task (not linked to another
task) at an arbitrary date (e.g. October 22, 2004) other than project
start date?
You can set a fixed date in the task view, by clicking the start date 
and choosing for example "must start on".
2) The Zoom In / Out for formatting the date headers is extremely
limiting (e.g. Week 28 ?!) . Is there any way to specify directly what
you want the date headers to be formatted regardless of the Zoom level?
No. I can't think of a way to make that work well in practice, since the 
available space to fill varies depending on the zoom level. I've been 
thinking about using a tooltip or the status bar to show accurate 
information when hovering over the header though. Do you think that 
would that help?
/Richard

--