Hi again,
Fact is, you could assign the same resource to 2 concurent tasks, but
with a 50% rate on both. You would notice that doing so, your task
duration will double and result in a 100% job of the resource.
If you keep a 100%(unit) on the same resource, you will see that the
resource has too much job(red color) on the "Resource usage" part.
Massimo
Le jeudi 03 mars 2005 �5:01 +0100, Josep Mon�i Teixidor a �it :
> El dj 03 de 03 del 2005 a les 13:56 +0100, en/na Max Lists va escriure:
> > Hi,
> >
> > You have to "link" the 2 sub task to tell task2 goes after task1.
> >
> > File attached.
> >
>
> Ah Ok! I knew I could do it this way but I expected the software to do
> that automatically, because tasks aren't conceptually sequential, it's
> just a resource problem. If I assign, for instance, task2 to another
> resource, I have also to remember unlinking it (and possibly unlinking
> and relinking many tasks which depended on task2).
>
> Thanks very much.
>
> Josep
>
>
>
> _______________________________________________
> Planner mailing list
> Planner lists imendio com
> http://lists.imendio.com/mailman/listinfo/planner
[
Date Prev][
Date Next] [
Thread Prev][
Thread Next]
[
Thread Index]
[
Date Index]
[
Author Index]