I've looked at the planner file you sent me, but I've been unable to
reproduce the problem.
A few more questions:
- Does the problem occur with all tasks?
I see some of the tasks in the file already have a completion > 75%
- Does the problem occur with newly created files?
- Do none of the ways of changing completion work:
* dragging completion in the gantt chart?
* using the "Edit task properties" dialog?
* enabling the "% Complete" column next to the gantt chart and editing
there?
Regards,
Maurice.
--
Maurice van der Pot
Gentoo Linux Developer griffon26 gentoo org http://www.gentoo.org
Gnome Planner Developer griffon26 kfk4ever com http://live.gnome.org/Planner
Attachment:
pgpKIwMY9GL41.pgp
Description: PGP signature