Re: Planner-list Irregular vacation dates
- From: fox <fox orbitalfox com>
- To: Alexandre Franke <alexandre franke gmail com>
- Cc: planner-list gnome org
- Subject: Re: Planner-list Irregular vacation dates
- Date: Fri, 18 Feb 2011 10:27:17 +0000
On 17/02/11 15:49, Alexandre Franke wrote:
> On Thu, Feb 17, 2011 at 3:09 PM, fox <fox orbitalfox com> wrote:
>> Hi,
>
> Hi.
>
>> Is there a way to have irregular vacation dates for resources? If yes,
>> do they remove the resource from a tasks completion time calculation?
>
> Yes. In resource view, edit rescource, go to calendar tab, edit
> calendars and simply set vacation days as non-working days for the
> calendar you'll assign to this resource.
>
> P.S.: you should subscribe to the mailing list if you want to get
> answers for your questions. I had to manually accept your mail as
> posts from non-subscribed people are moderated.
>
Thank you this worked!
It would be nice if there was an indication in the month view that the
resource is unavailable (e.g. greyed out).
But it does recalculation completion time.
[