Re: [Planner Dev] The link tasks dialog - screenshot.
- From: Richard Hult <richard imendio com>
- To: Planner Project Manager - Development List <planner-dev lists imendio com>
- Subject: Re: [Planner Dev] The link tasks dialog - screenshot.
- Date: Tue, 13 Apr 2004 14:55:32 +0200
On tis, 2004-04-13 at 13:49 +0100, Lincoln Phipps wrote:
> >>When its a second, minute or hour then no problems. Its when we talk
> >>about 1 day or 1 week that there is a user understanding difference
> >>between a calendar/elapsed day/week/month and a working day/week/month.
> >
> >
> > I was mostly concerned that you don't realize you can type in 1d, 1w, 1h
> > etc. I've had a couple of different users wondering how to create tasks
> > with time less than a 1d since they didn't realize '1h' was possible.
> >
>
> This is actually new functinality as the existing lag in the task
> predecessor lag cell is hard coded as "hours" anyway - which needs to
> be changed (bugzilla raised a while ago by me).
I think Mikael is referring to the fact that it's equally hard to notice
in the existing places (task/gantt views).
> The tooltip should highlight this new capability of adding 1h, 1d, 1w etc.
Could help in the dialogs but not really in the views.
/Richard
--