Re: [Planner Dev] Cost computation - some test cases
- From: Lincoln Phipps <lincoln phipps openmutual net>
- To: Planner Project Manager - Development List <planner-dev lists imendio com>
- Subject: Re: [Planner Dev] Cost computation - some test cases
- Date: Sun, 18 Apr 2004 13:49:16 +0100
Xavier Ordoquy wrote:
Here are some cost computation sample. I'll try to make them test cases
when the Python binding will be available.
Here's a sample plan thats matches your test cases - note I've created a
Resource 3 so it can have a cost of 25/h.
Lincoln.
=================================================================
Test case 1
Resource R1: cost is 12.5 (100 per day)
Tasks T1: work is one day, R1 assigned 100%
T1:
Duration should be one day
Cost should be 100
=================================================================
Test case 2
Resource R1: cost is 12.5 (100 per day)
Tasks T1: work is one day, R1 assigned 50%
T1:
Duration should be 2 days
Cost should be 100
=================================================================
Test case 3
Resource R1: cost is 12.5 (100 per day)
Tasks T1: work is two day, R1 assigned 200%
T1:
Duration should be 1 days
Cost should be 200
=================================================================
Test case 4
Resource R1: cost is 12.5 (100 per day)
Resource R2: cost is 12.5 (100 per day)
Tasks T1: work is two day, R1 and R2 assigned 100%
T1:
Duration should be 1 days
Cost should be 200
=================================================================
Test case 5
Resource R1: cost is 12.5 (100 per day)
Resource R2: cost is 12.5 (100 per day)
Tasks T1: work is 3 day, R1 assigned 100%, R2 assigned 50%
T1:
Duration should be 2 days
Cost should be 300
=================================================================
Test case 6
Resource R1: cost is 12.5 (100 per day)
Resource R2: cost is 25 (100 per day)
Tasks T1: work is 3 day, R1 assigned 100%, R2 assigned 50%
T1:
Duration should be 2 days
Cost should be 400
_______________________________________________
Planner-dev mailing list
Planner-dev lists imendio com
http://lists.imendio.com/mailman/listinfo/planner-dev
<?xml version="1.0"?>
<project name="Task Cost Test Cases" company="" manager="" phase="" project-start="20040418T000000Z" mrproject-version="2" calendar="1">
<properties>
<property name="cost" type="cost" owner="resource" label="Cost" description="standard cost for a resource"/>
</properties>
<phases/>
<calendars>
<day-types>
<day-type id="0" name="Working" description="A default working day"/>
<day-type id="1" name="Nonworking" description="A default non working day"/>
<day-type id="2" name="Use base" description="Use day from base calendar"/>
</day-types>
<calendar id="1" name="Default">
<default-week mon="0" tue="0" wed="0" thu="0" fri="0" sat="1" sun="1"/>
<overridden-day-types>
<overridden-day-type id="0">
<interval start="0800" end="1200"/>
<interval start="1300" end="1700"/>
</overridden-day-type>
</overridden-day-types>
<days/>
</calendar>
</calendars>
<tasks>
<task id="1" name="TEST1" note="" work="28800" start="20040418T000000Z" end="20040419T170000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
<task id="2" name="T1-TASK1" note="Duration should be 1.0 Day, Overall cost should be 100." work="28800" start="20040418T000000Z" end="20040419T170000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work"/>
</task>
<task id="3" name="TEST2" note="" work="57600" start="20040418T000000Z" end="20040420T170000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
<task id="4" name="T2-TASK1" note="Duration should be 2 Days, Overall cost should be 100." work="28800" start="20040418T000000Z" end="20040420T170000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work"/>
</task>
<task id="5" name="TEST3" note="" work="28800" start="20040418T000000Z" end="20040419T170000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
<task id="6" name="T3-TASK1" note="Duration Should be 1 Days, Overall cost should be 200." work="57600" start="20040418T000000Z" end="20040419T170000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work"/>
</task>
<task id="7" name="TEST4" note="" work="28800" start="20040418T000000Z" end="20040419T170000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
<task id="8" name="T4-TASK1" note="Duration Should be 1 day, Overall cost should be 200." work="57600" start="20040418T000000Z" end="20040419T170000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work"/>
</task>
<task id="9" name="TEST5" note="" work="57600" start="20040418T000000Z" end="20040420T170000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
<task id="10" name="T5-TASK1" note="Duration should be 2 days, Overal cost should be 300." work="86400" start="20040418T000000Z" end="20040420T170000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work"/>
</task>
<task id="11" name="TEST6" note="" work="57600" start="20040418T000000Z" end="20040420T170000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work">
<task id="12" name="T6-TASK1" note="Duration should be 2 Days, Overall cost should be 400." work="86400" start="20040418T000000Z" end="20040420T170000Z" percent-complete="0" priority="0" type="normal" scheduling="fixed-work"/>
</task>
</tasks>
<resource-groups/>
<resources>
<resource id="1" name="R3-25" short-name="" type="1" units="0" email="" note="" std-rate="25">
<properties>
<property name="cost" value=""/>
</properties>
</resource>
<resource id="2" name="R2-12.5" short-name="" type="1" units="0" email="" note="" std-rate="12.5">
<properties>
<property name="cost" value=""/>
</properties>
</resource>
<resource id="3" name="R1-12.5" short-name="" type="1" units="0" email="" note="" std-rate="12.5">
<properties>
<property name="cost" value=""/>
</properties>
</resource>
</resources>
<allocations>
<allocation task-id="12" resource-id="1" units="50"/>
<allocation task-id="10" resource-id="2" units="50"/>
<allocation task-id="8" resource-id="2" units="100"/>
<allocation task-id="12" resource-id="3" units="100"/>
<allocation task-id="10" resource-id="3" units="100"/>
<allocation task-id="8" resource-id="3" units="100"/>
<allocation task-id="6" resource-id="3" units="200"/>
<allocation task-id="4" resource-id="3" units="50"/>
<allocation task-id="2" resource-id="3" units="100"/>
</allocations>
</project>
[