[Planner Dev] MS Project "red flag"
- From: Mark Durrenberger <m durrenberger comcast net>
- To: Planner Project Manager - Development List <planner-dev lists imendio com>
- Subject: [Planner Dev] MS Project "red flag"
- Date: Wed, 11 Feb 2004 14:32:52 -0500
The resource management tools in MS Project are a pain in the neck at best
and dangerous at worse - primarily because of the assumptions the
developers made and poor terminology they used while implementing
- hopefully the explanations below will keep you from making the same
mistakes... (Pardon me if my tone is a bit "pompous" this topic is
important to me and I have strong views - so if you'll allow me to "rant"
for a moment...)
First some background:
Effort - the number of labor hours (days, weeks) required to accomplish a
project activity. A consultant usually bills on his or her effort - so
think of "how many hours would I have to pay a consultant to do this work"
Duration - the number of days (weeks) that it takes to complete a project
activity. 1 week is typically thought of as five days of duration.
Example 1: A consultant might say - well that's about 35 hours worth of
work and I can have it for you a week from Friday. So the task is 35 hours
of effort and 9 days of duration. (Thursday, Friday, and Monday through
Friday of the next week assuming we are not counting weekends)
Example 2: I am creating a 1/2 day course for a client. It takes me about
6 hours of effort to pull together the slides for the course. However
accounting for interruptions (e-mails like these) it will take a day to
complete the task (to make it easy, I usually think of effort in
staff-hours (man-hours) and duration in days this helps avoid the confusion
of units.)
Now the "wrong way" to do this :-) (Microsoft Project MSP for short)
MSP calls effort "Work." Work is ambiguous. Effort is better.
MSP uses units of hours or days - neither is sufficient man-hours (days) is
better, staff-hours (days) is even better (out of respect for the working
women in the world)
In MSP, Once you have assigned a resource to an activity in the effort and
duration become "linked" that is, if you change the duration of the task,
MSP recalculates the effort (Work). Change the effort and MSP recalculates
the duration - the assumption is 8 hours per day, 40 hours per week unless
you change the default values or change the calendar for the assigned resource.
Why this is wrong - In theory, effort and duration should be linked. In
practice they never are (8 years now, I've never seen it work, and I look).
People don't use the resource allocation tools in MSP because changes in
duration cause changes in effort. I believe the primary reason that people
don't want the two linked is "time slicing." Most organizations have too
many projects, so people have to switch from project to project on a
regular basis. MSP says 40 hours effort = 5 days duration. Reality says
"never happen" (well in the rare case that someone is 100% on one project
it *might* happen. To see why I say this answer this question: "How many
hours must I work in a day to get 8 productive hours?" I'm guessing your
answer will be somewhere between 10 and 12 depending on the nature of your
job.)
When people plan projects, they factor in the interruptions but don't
express them as allocation percent. Like the consultant example above,
they'll tell you 35 hours, 9 days (FYI that's 48.6% allocation assuming 8
hours a day) so why force it. Just take the data ...
Some Work Arounds in MSP
1) Don't assign resources - Until you assign resources effort and duration
are not linked. (Instead create a column called "Accountable" and put names
in the accountable field. However, then it's hard to determine how many
hours each accountable person is assigned)
Use the built in flags:
"Fixed Duration" - changing the effort does not change the duration,
"Fixed Work" - changing the duration does not change the effort.
"Fixed Units" - changes in either duration or effort does not change the %
allocation (no matter how long the duration or how large the effort, the %
allocation stays the same - so MSP tweaks the others)
The flags help but if you change the work on a fixed work task, the
duration will change and if you change duration on a fixed duration task,
the work will change
(FYI "Units" should be called "allocation percent" or "percent allocated" )
Effort and duration should, by default, be unlinked. Give the user the
option to link the two (I'm betting most will not).
Does this make sense?
I can expand any point.
Next topic - estimating effort vs. duration
Regards,
Mark
At 12:18 PM 2/11/2004, you wrote:
I too noticed defining resources wasn't easy at first.
As a quick fix for next release of Planner can I
suggest a simple button/menu of "Allocate Resources"
Thus you could ctrl/shift-click multiple tasks (well
actually I've found up to 31 or 32 only !) and then
click/menu the "Allocate resources" option.
Something like the existing Resource display would be
presented but existing allocations would be presented
in the typical (true for GNOME ?) three-state
convention of Checked , Not Checked and Inconsistent
based on all the resource allocations of all the
selected tasks.
Thus you could easily add/remove a resource and adjust
its units allocation but keep existing allocations
unchanged, across all the selected tasks at once.
Does that sound OK ?. I can look at this as I've finished
my "Link" button change and this change would be a nice
incrementally more difficult task for me. I won't be
able to do a drag-n-drop as that would be too hard
(my guess).
OK for this ?
Rgds,
Lincoln.
(After that we'd need a easy way of setting completion
percentage for many tasks ;)
_______________________________________________
Planner-dev mailing list
Planner-dev lists imendio com
http://lists.imendio.com/mailman/listinfo/planner-dev
From ghoulies and ghosties and long leggedy beasties and things that go
bump in the night, good lord deliver us.