Re: [Planner Dev] MS Project "red flag"



Just caught an error below



When people plan projects, they factor in the interruptions but don't express them as allocation percent. Like the consultant example above, they'll tell you 35 hours, 9 days (FYI that's 48.6% allocation assuming 8 hours a day) so why force it. Just take the data ...

35 hours, 7 days duration (not 9) 62.5% allocation assuming an 8 hour day