Re: [Planner Dev] MS Project "red flag"



tis 2004-02-17 klockan 16.20 skrev Mark Durrenberger:

> I'm having a tough time coming up with good reasons to link effort and 
> duration but  I can't rule it out for others. So it might be a feature some 
> (former MSP users) would look for - is that justification enough to include 
> it?

I think the feature is mostly used in MS Project as a way to do
"what-if" scenarios, where you add a few resources to see what the
result is. The problem with the way it is presented in the UI is that
you sort of buy the whole thing as a truth ("wow, if I add 10 resources,
the project will be done a month in advance"). 

I'm sure there are many other ways to achieve the same thing in a better
way.

We should probably keep the feature in some form though, since there
actually IS a relationship between the duration and the amount of
resources that you throw at a task, even if it's not really linear like
in our model. For resources other than human it might even be a very
good estimation.

I definitely agree that it would probably be better to not have the
relationship enabled by default. 

> User selects a task flag "link effort and duration" once this flag is 
> toggled, then they are presented with three additional "check boxes"
> 
> "Keep duration constant" (is that better than "fixed duration"?) (default)
> "Keep effort constant"
> "keep allocation % constant" (please don't use "units")

I like this, I think it would be a very nice way to deal with it.

Thanks for the input!
Richard

-- 
Richard Hult                    richard imendio com
Imendio                         http://www.imendio.com