Re: [Planner Dev] Incorrect Start Dates in Tasks View
- From: Richard Hult <richard imendio com>
- To: Planner Dev <planner-dev lists imendio com>
- Subject: Re: [Planner Dev] Incorrect Start Dates in Tasks View
- Date: Tue, 08 Jun 2004 01:14:08 +0200
On tis, 2004-06-08 at 00:00 +0100, lincoln phipps openmutual net wrote:
>
> John_Minkle huntalternatives org wrote:
> >
> > An example: Task A is a one Day Task that takes place Friday and it is
> > linked to Task B. Task B shows that it starts on Friday in the Tasks
> > View. But in the Gantt View it is clear that the task does not start
> > until Monday.
>
> Yes - you're right ! Odd - that can't have been the behaviour
> since day-1. Thats got to be something new since 0.11.
I'm pretty sure it's always been there actually :) It only shows up for
tasks that end right before non-working time though.
/Richard
--
Imendio HB, http://www.imendio.com/
[