On tis, 2004-06-08 at 00:00 +0100, lincoln phipps openmutual net wrote:
> 
> John_Minkle huntalternatives org wrote:
> > 
> > An example: Task A is a one Day Task that takes place Friday and it is 
> > linked to Task B.  Task B shows that it starts on Friday in the Tasks 
> > View. But in the Gantt View it is clear that the task does not start 
> > until Monday.
> 
> Yes - you're right ! Odd - that can't have been the behaviour
> since day-1. Thats got to be something new since 0.11.

I'm pretty sure it's always been there actually :) It only shows up for
tasks that end right before non-working time though.

/Richard

-- 