Charles Tryon wrote:
On Wed, 2004-05-19 at 18:51, Richard Hult wrote:
On ons, 2004-05-19 at 17:28 -0400, Charles Tryon wrote:
I've seen the dialog box, but I still didn't find any place to assign
either a start or finish date.
You need to select the Task view and click the start date cell and
select a "Must start on" constraint (or "Start no earlier than").
Ah! Very Good!
I'd argue that the UI for setting specific dates on a task should be a
part of the "Edit Task" dialog, perhaps as another tab, but I don't know
And you're right ! - I'm working on a dialog to do this but other
work and the UNDO/REDO for the 0.12 takes precedence right now ;)
Rgds,
Lincoln.
what other problems that might cause. (My apologies if this has already
been hashed out in this forum before.)
/Richard
_______________________________________________
Planner-dev mailing list
Planner-dev lists imendio com
http://lists.imendio.com/mailman/listinfo/planner-dev
[
Date Prev][
Date Next] [
Thread Prev][
Thread Next]
[
Thread Index]
[
Date Index]
[
Author Index]