Re: [Planner Dev] Fixed dates on tasks?





Charles Tryon wrote:

On Wed, 2004-05-19 at 18:51, Richard Hult wrote:

On ons, 2004-05-19 at 17:28 -0400, Charles Tryon wrote:

 I've seen the dialog box, but I still didn't find any place to assign
either a start or finish date.

You need to select the Task view and click the start date cell and
select a "Must start on" constraint (or "Start no earlier than").


  Ah!  Very Good!

  I'd argue that the UI for setting specific dates on a task should be a
part of the "Edit Task" dialog, perhaps as another tab, but I don't know


And you're right ! - I'm working on a dialog to do this but other
work and the UNDO/REDO for the 0.12 takes precedence right now ;)

Rgds,
Lincoln.


what other problems that might cause.  (My apologies if this has already
been hashed out in this forum before.)


/Richard


_______________________________________________
Planner-dev mailing list
Planner-dev lists imendio com
http://lists.imendio.com/mailman/listinfo/planner-dev




[Date Prev][Date Next]   [Thread Prev][Thread Next]   [Thread Index] [Date Index] [Author Index]